10.1 General Requirements
10.1.1 The construction planning shall be compiled based on the following data:
1 The construction-related hydrological,meteorological,topographical and geological information and corresponding design results of the hydropower station.
2 Social conditions of the region where the hydropower station is located.
3 Opinions and requirements from the superior authority or the owner on the construction planning.
10.1.2 The construction planning shall be compiled under the following principles:(https://www.daowen.com)
1 Complying with the relevant laws,regulations,technological and economic policies.
2 Integrating with status quo and accommodating to the local conditions,coordinating construction and environmental protection to the best.
3 Making overall arrangement,comprehensively balancing and properly coordinating the constru-ction at various parts of the project to ensure construction safety.
4 Promoting new technology,new materials,new workmanship and new equipment in a positive and prudent way.