《GB 50071-2014小型水力发电站设计规范:英文》简介
《GB 50071-2014小型水力发电站设计规范:英文》这本书是由.中国工程建设标准化协会组织编译创作的,《GB 50071-2014小型水力发电站设计规范:英文》共有102章节
1
中华人民共和国住房和城乡建设部公告
第1128号 住房城乡建设部关于发布《小型水力发电站设计规范》等两项国家标准英文版的公告 现批准《小型水力发电站设计规范》GB 50071-2014、《小型水电
2
Introduction to English Version
Department of International Cooperation,Science and Technology of Ministry of Wa
5
1 General Provisions
1.0.1 This Code is formulated to satisfy the needs for construction and developm
7
2.1 General Requirements
2.1.1 In hydrological analysis and computation,the following data shall be colle
10
2.4 Rating Curve
2.4.1 If there is a hydrometrical gauging station in the vicinity of the dam(pla
11
2.5 Sediment,Evaporation,Ice Regime
2.5.1 All or part of the following sediment information at the dam(plant)site sh
12
2.6 Automatic Hydrological Telemetry System
2.6.1 The necessity for setting up an automatic hydrological telemetry system sh
14
3.1 General Requirements
3.1.1 Engineering-geological investigation shall include basic geological condit
15
3.2 Regional Geology
3.2.1 Available regional geological data of project site shall be studied to loc
16
3.3 Engineering Geology of Reservoirs
3.3.1 The investigation of reservoir seepage shall include: 1 Existence of thin
17
3.4 Engineering Geology of Hydraulic Structures
3.4.1 The investigation into the site of an earth-rock dam shall include: 1 Stra
18
3.5 Natural Construction Material
3.5.1 For natural building materials,an initial investigation or detailed invest
20
4.1 General Requirements
4.1.1 The principle of integrated water resources management shall be insisted i
21
4.2 Computation of Runoff Regulation
4.2.1 In the computation of runoff regulation,the data that shall be gathered in
22
4.3 Flood Regulation and Selection of Characterist...
4.3.1 In the computation of flood regulation,techno-economic comparison shall be
23
4.4 Selection of Normal Water Level and Dead Water...
4.4.1 For the selection of normal storage level,several options shall be formula
24
4.5 Selection of Installed Capacity and Type of Hy...
4.5.1 Installed capacity shall be selected on the basis of analysis of regulatin
25
4.6 Selection of Dimensions of Power Waterway and ...
4.6.1 For diversion type hydropower stations,the dimensions of headrace and the
26
4.7 Analysis of Reservoir Sedimentation and Backwa...
4.7.1 If the ratio of storage capacity to annual sediment volume flowing into th
27
4.8 Reservoir Operation Mode and Operational Chara...
4.8.1 The reservoir operation mode shall be proposed based on the defined parame
29
5.1 General Requirements
5.1.1 The scales of projects and the grades of structures shall meet the followi
30
5.2 General Layout of Project
5.2.1 Dam site(or dam axis)and powerhouse site shall be selected after techno-ec